If you’ve driven through the I-135 and Kellogg interchange recently, you’ve probably noticed construction barriers, closed ramps and heavy equipment along one of Wichita’s major highway connections.
For motorists who depend on the interchange to get to work, school and other destinations, the construction raises three questions: What’s being built? Why is the work necessary? And when will drivers be able to travel through the interchange without construction disruptions?
The Kansas Department of Transportation (KDOT) is replacing one bridge and rehabilitating another where I-135 meets U.S. 54, commonly known as Kellogg.

J.B. Wilson, KDOT’s Wichita Metro Public Information Officer, spoke with The Community Voice about the project and what drivers can expect when the work is finished.
Two Bridges, Two Different Approaches
The construction involves two ramps connecting I-135 and Kellogg, each requiring a different approach because of the condition of its existing structure.
The bridge carrying southbound I-135 traffic to eastbound Kellogg has reached the end of its service life and is being replaced entirely.
Crews are building the new bridge parallel to the existing structure, allowing the original ramp to remain available while the replacement is constructed.
“We’re going to essentially migrate traffic to the new ramp, and then we’re going to demolish the old one,” Wilson said.
The northbound I-135 ramp to westbound Kellogg requires a different type of work. Its supporting structure remains serviceable, but the concrete deck motorists drive across has reached the end of its useful life.
Crews are replacing that surface through a process called redecking, which removes and rebuilds the roadway portion of the bridge while retaining the supporting structure.
Wilson explained that KDOT handles maintenance and rehabilitation differently from projects intended to modernize or expand highways. Rehabilitation restores aging infrastructure, while expansion projects may add lanes, redesign ramps or increase roadway capacity.
“We’re not enhancing that connectivity; we’re rehabilitating it,” Wilson said.
The replacement bridge will serve the same traffic movement as the existing bridge, and the redecked structure will keep its original configuration.
Will the Improvements Reduce Traffic Backups?
Motorists traveling through the interchange often encounter congestion where vehicles enter and exit Kellogg, particularly during busy commuting periods.
One trouble spot is the southbound I-135 connection to eastbound Kellogg. Drivers also encounter merging traffic where vehicles entering eastbound Kellogg from northbound and southbound I-135 come together.
Wilson said the current construction is not designed to expand the interchange or substantially change how traffic moves through it.
When asked whether the replacement bridge would be wider or include additional lanes, Wilson explained that it would follow essentially the same design as the existing structure.
That means the project is not expected to eliminate recurring traffic backups through additional lanes or redesigned merging areas.
Instead, drivers will gain renewed bridge structures that allow the existing highway connections to remain in service.
The northbound I-135 ramp to westbound Kellogg has been closed during rehabilitation. KDOT’s published detour directs drivers to continue north to the Second Street exit, return southbound on I-135 and then connect to westbound U.S. 54.
Construction has also required closures of inside lanes along I-135 between Lincoln Street and Douglas Avenue during portions of the project.

These restrictions give workers room to remove concrete, position equipment and complete bridge construction while traffic continues moving through nearby highway connections.
Wilson explained that traffic-control plans must be coordinated with contractors and engineers, particularly when construction requires specialized operations such as concrete placement.
Because those activities depend on construction schedules, some closures and detours are announced only after the necessary plans are finalized.
Drivers can check current traffic restrictions and alternate routes through KanDrive, the state’s traveler information service, at kandrive.gov.

When Will Construction Be Completed?
Wilson said KDOT anticipates completing the I-135 and Kellogg interchange project by December 2027.
He explained that the completion date is an estimate because weather conditions, contractor schedules and other construction-related factors can affect when work is finished.
The department must coordinate those activities while keeping surrounding highway connections available to motorists whenever possible.
For Wichita drivers, the finished project will mean a newly constructed bridge carrying southbound I-135 traffic onto eastbound Kellogg and a rehabilitated bridge connecting northbound I-135 to westbound Kellogg.
The interchange will retain essentially the same layout, with renewed infrastructure intended to keep those connections available for years to come.